DACI Decision Framework
Overview
Clarify decision ownership and reduce decision thrash using the DACI framework (Driver, Approver, Contributor, Informed). Unlike RACI which focuses on task responsibility, DACI is purpose-built for product decisions -- who drives the decision to closure, who has veto power, who provides input, and who needs to know.
The four roles in brief: Driver (exactly one, drives to closure), Approver (1-2 max, holds veto), Contributor (input without veto), Informed (notified, not consulted). Build a chart by mapping current state, finding pain points, designing target state, and rolling out a 30/60/90 transition. See the playbook reference for role rules, the 7-step build sequence, and health metrics.
When to Use
- New team formation -- A new cross-functional group needs clear decision-making roles.
- Decision thrash -- Decisions stall because nobody knows who has authority.
- Scaling teams -- Growth creates ambiguity about who owns which decisions.
- Post-incident -- A failed launch or missed deadline reveals unclear ownership.
- Reorg transitions -- Role changes create governance gaps.
When NOT to Use
- Task assignment or project execution (use RACI instead).
- Individual contributor work allocation (use sprint planning).
- Truly one-person decisions (no governance overhead needed).
Clarify First
Before building the DACI chart, settle the inputs below. When one is missing or vague and would change the result, ask about it; when it wouldn't, use a sensible default and say which one you used.
- The specific decisions to map: the 3-5 high-impact decisions, not "everything" (each becomes a chart row; mapping too much at once is the top failure mode).
- Candidate people and their real authority: who can actually approve or veto (drives the Driver and Approver assignments; without genuine authority the chart is fiction).
- Current pain points: where decisions stall or thrash today (drives the current→target-state gap and the 30/60/90 transition plan).
Ask about the two or three inputs that matter most for this request, not the whole list. If the user wants a result straight away, produce it and state your assumptions at the top.
Anti-Patterns
Informed roles that object late
Mistake: Marketing is marked Informed on the launch date, objects three days before launch, and the date slips two weeks. Why it happens: Teams mark a role Informed to keep meetings small, without asking whether that role can block the decision. Instead: Make anyone who can stop the decision a Contributor or Approver from the start. Once the decision locks, a late objection goes to the Approver as an escalation.
Everyone marked Contributor
Mistake: Most cells in the chart are C, so everyone expects to be consulted on everything. Why it happens: Assigning C avoids hard conversations about who is left out. Instead: Per decision, assign one D, one or two A, and at most 3-4 C. Give C only to roles with real expertise to add, and mark the rest I or leave them blank. More than 5 C cells on a row is a flag.
Vetoes with no written reason
Mistake: The Driver proposes option A and the Approver says "No" with no follow-up. Two months later the same debate returns. Why it happens: A veto feels like the end of the matter, so writing it up seems optional. Instead: Ask Approvers to give every veto a written rationale and say what a counter-proposal would need to address. Keep these as decision records, and check the last 5 vetoes for them.
Nine more, each with a bad and a good example: references/red-flags.md.
References
- references/playbook.md — read this when building or running a DACI chart: role definitions and rules, the 7-step build sequence (working group → roles → decisions → current-state map → pain points → target-state → transition plan), governance health metrics, troubleshooting, and success criteria.
- references/red-flags.md — read this before publishing a chart or running a decision under it: common ways a DACI chart goes wrong with bad/good examples anchored to the role rules.
Scope & Limitations
In Scope: DACI chart creation, current-state mapping, target-state design, transition planning, governance health metrics, pain point identification, decision ownership clarity.
Out of Scope: Task assignment (use RACI), project execution tracking (use sprint planning), individual performance management, organizational design beyond decision governance.
Important Caveats: DACI works best when leadership commits to respecting the framework. Without executive buy-in, Drivers may lack the authority to actually drive decisions. Start with 3-5 high-impact decisions rather than trying to map everything at once.
Integration Points
| Integration | Direction | What Flows |
|---|---|---|
create-prd/ |
Feeds into | DACI decisions inform PRD Contacts section and decision log |
identify-assumptions/ |
Complements | Surfaces assumptions about who has authority |
brainstorm-okrs/ |
Complements | OKR ownership aligns with DACI decision ownership |
summarize-meeting/ |
Feeds into | Meeting summaries capture DACI decision outcomes |
senior-pm/ |
Complements | Portfolio-level DACI for cross-project decisions |
Further Reading